It is almost two years since Rapid Builders & Contractors vacated a construction site meant for building a R68-million clinic in New Eersterust, Hammanskraal, Pretoria. Residents have now turned the site into a dumping area. There is confusion about why the project stopped, according to GroundUp. The Gauteng Department of Infrastructure Development (GDID) awarded Rapid Builders the tender on 30 November 2016. What was supposed to have been an 11-month project came to a halt in September 2019 as disputes among members of the project committee and business forums saw the contractor vacate the area. This is according to GDID spokesperson Bongiwe Gambu.”The contractor voluntarily left the site citing the involvement of business forums on the project as an issue,” Gambu said. When GroundUp visited the site recently, residents had started using it as a dumping site. The fence that had barricaded the area was no longer there, but a construction site sign remained, indicating Rapid Builders as the contractor. Gambu said 15% of the budgeted funds have been used. Early last year, Rapid Builders project manager Shane Govindasamy told GroundUp they would not successfully complete the work due to constant interruptions by the community.

“The situation was out of control. The community didn’t allow us to work. When we brought our own machinery on-site, they wanted to bring their own. They wouldn’t allow us to work for three days straight. They would protest because they wanted a slice of the cake,” he said at the time. It is common that so-called “business forums” try to get in on the action when new large developments are started. This makes it hard for legitimate companies, especially ones that do not wish to pay what they may see as bribes, to finish developments. Previously, we failed to locate the business forums in question but recently tracked down the project’s Community Liaison Officer Isaac Komane, as well as Meyer Mtshweni, the New Eersterust business forum chairperson.

According to Komane, before work began, he received submissions from residents wishing to offer various services at the project. Those who dealt with construction machinery were welcome to outsource if they didn’t have their own. But then it appears things became chaotic. “Different groups started coming up,” he said. “I had lists of local businesses from the community that had submitted but people bringing machinery weren’t on my list. The groups were against each other. One group would bring a machine. Another group would object and come with theirs, which caused conflict,” said Komane. He said the contractors would often find themselves without equipment to perform their duties, which would halt the process for days and sometimes weeks.

“A site manager in 2019 said he couldn’t work that way. Because of constant disagreements, they sometimes worked… one day a week.” Asked about the business forums in the community, Komane said “business forum” was just a name. Resident and street vendor Dinah Mafodi said most of the residents had no idea what was happening with the project and why it had stopped. “We saw construction vehicles stationed at the site and we were excited that finally another clinic was going to be built. This area grew larger and a new clinic would surely assist those that do not live near the current clinic,” said Mafodi. Naledi Dube, also a resident, said: “We have never had any formal communication regarding the clinic. These are just rumours we heard. We also heard that the clinic was going to operate 24 hours. That was going to be a relief because if a family member gets sick, then we wouldn’t have to go far.”

QUESTION 1 (15 MARKS)

The R68-million clinic project faced several challenges which potentially would have affected its quality upon completion. Critically discuss the quality related challenges that Shane Govindasamy was exposed to during project implementation.

QUESTION 2 (15 MARKS)

With reference to the case study provided critically discuss the elements that Rapid Builders & Contractors would have considered in putting together their project quality management plan.

Answers to Above Question on Project Management

Answer 1: Quality management is highly essential in every type of project. In the given case study on Rapid Builders and contractors, it is evaluated that there are significant changes related to quality management being faced by the company. Some of these challenges are inadequate planning with respect to project activities, poor communication throughout the project, limited resources, no specific standard to measure the quality level etc.

answer

Get completed answers on the questions above on project management from the best writers of Student Life Saviour in South Africa.


Content Removal Request

If you believe that the content above belongs to you, and you don’t want it to be published anymore, then request for its removal by filling the details below. It will only be removed if you can provide sufficient evidence of its ownership.

    March
    January
    February
    March
    April
    May
    June
    July
    August
    September
    October
    November
    December
    2025
    1950
    1951
    1952
    1953
    1954
    1955
    1956
    1957
    1958
    1959
    1960
    1961
    1962
    1963
    1964
    1965
    1966
    1967
    1968
    1969
    1970
    1971
    1972
    1973
    1974
    1975
    1976
    1977
    1978
    1979
    1980
    1981
    1982
    1983
    1984
    1985
    1986
    1987
    1988
    1989
    1990
    1991
    1992
    1993
    1994
    1995
    1996
    1997
    1998
    1999
    2000
    2001
    2002
    2003
    2004
    2005
    2006
    2007
    2008
    2009
    2010
    2011
    2012
    2013
    2014
    2015
    2016
    2017
    2018
    2019
    2020
    2021
    2022
    2023
    2024
    2025
    2026
    2027
    2028
    2029
    2030
    2031
    2032
    2033
    2034
    2035
    2036
    2037
    2038
    2039
    2040
    2041
    2042
    2043
    2044
    2045
    2046
    2047
    2048
    2049
    2050
    SunMonTueWedThuFriSat
    23
    24
    25
    26
    27
    28
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    12
    13
    14
    15
    16
    17
    18
    19
    20
    21
    22
    23
    24
    25
    26
    27
    28
    29
    30
    31
    1
    2
    3
    4
    5
    00:00
    01:00
    02:00
    03:00
    04:00
    05:00
    06:00
    07:00
    08:00
    09:00
    10:00
    11:00
    12:00
    13:00
    14:00
    15:00
    16:00
    17:00
    18:00
    19:00
    20:00
    21:00
    22:00
    23:00